Brandt Engineered Products Ltd. Regina, SK
  • Recently named one of Canada’s 50 Best Managed Companies
2
Objectives
  •    To increase annual production while reducing customer lead times and internal cycle times by:
    • Reducing current lead time from 23 days
    • Reducing input costs per cylinder
    • Eliminating delays due to   departmentalized production processes

3
Lean Solutions
  • Measured all component parts in terms of time to produce, distance travelled, and machinery/processes utilized to produce these parts.
  • Designed and implemented a manufacturing cell to include all possible machines such as milling, lathe, welding, assembly, testing, etc.


4
Before
5
During
6
After
7
Lean Results